Red Alert!  The country is in lock down, supermarket shelves are empty and there's not a loaf of bread to be had.  Schools are shut. Public transport has ground to a halt.   Hysteria has not even escaped the Taoiseach. 

Construction sites are no exception during these inclement snow days.   Contractors and subcontractors cannot put their teams to work on site. However they still have to pay their staff if they have not forced them to take annual leave.  Either which way they are at a loss because days have been lost under the programme.  If they are found to have delayed the practical completion date then the employer  will not waste time attempting to fix the contractor for LAD's (Liquidated and Ascertained Damages) and likewise the contractor against the subcontractor.    

Standard forms of construction contracts contemplate such a scenario whereby an extension of time or compensation is payable to the subcontractor if they cannot work on site due to a 'Weather Event'.

You might think that a delay/compensation claim for a 'weather event' like the one we are experiencing is straight forward but, think again.  

The Public Works contracts (PW-CF1 to PW-CF7) are very convoluted when it comes to extension of time claims for inclement weather. The closest Met Éireann weather station's average monthly records for rain, wind and temperature are incorporated into the contract.  These averages must be measured against the weather complained of to verify if it warrants classification as a 'Weather Event' for a delay claim or compensation claim to be allowable    

So for today's weather to be classified as a 'Weather Event'  under the PWC, the number of days where the temperature drops below 0 degrees Celcius in the month of February is 8 days and the number of days where precipitation exceeds 10mm is 3 days!  After all of that, you turn to schedule K to determine if a 'Weather Event' is a delay claim or a compensation claim or both.  

The RIAI contract is thankfully much simpler.  If works have been delayed because in the opinion of the architect there has been 'exceptionally inclement weather', then the architect grants a 'fair and reasonable' extension time under the programme.  

Either way the contractor and subcontractor must give immediate notice of the claim.  Otherwise the claim may be lost despite all of the logic and evidence.

I know which contract I'd rather be operating under.